BOND 18 PROJECTS ADDRESS:

  • Safety + Security
  • Technology
  • Immediate Needs
  • Building Efficiency
  • Building Sustainability (next 5 years)
    • Alamo Elementary School 
      • Repair existing built-up roof $100,000 
      • Replace existing thru-wall flashing $50,220 
      • Repair existing metal roofs $50,000 
      • Exterior brick work $50,000 
      • Replace chiller (100 ton) $270,000
        • FACILITY TOTAL $520,220
    • Coastal Village Elementary School (Rosenberg)
      • Replace modified bitumen roof $1,228,500
      • Replace thru-wall flashing $56,700
      • Electrical upgrades $60,750
      • Wet glaze windows $27,000
      • Replace exterior soft sealants $33,750
      • Replace carpet with VCT and tile front office $151,875
      • Install AHU control program and VAV $434,565
        • FACILITY TOTAL $1,993,140
    • Crenshaw Elementary/Middle School 
      • Treat outside metal porch decking $26,325 
      • Insulate under building $391,500 
      • Wet glaze exterior windows $27,000 
      • Replace exterior soft sealants $33,750 
      • Miscellaneous roof repairs $27,000 
      • Retrofit sprinkler heads under buildings $10,000 
      • Replace outside section of condenser pipe $141,750 
      • Replace office area A/C unit $86,400 
      • Outdoor ADA ramp $200,000
        • FACILITY TOTAL $943,725
    • Morgan Elementary School
      • Replace ceramic gym floor with VCT $24,300 
      • Replace front side canopy $151,200
      • Replace outside doors $68,850 
      • Replace exterior soft sealants $54,000 
      • Wet glaze windows $27,000 
      • Miscellaneous wall repairs $23,625 
      • Miscellaneous roof repairs $27,000 
      • Retrofit exterior LED marquee $35,000 
      • Replace boiler $111,240
        • FACILITY TOTAL $522,215
    • Oppe Elementary School
      • Replace built-up roof $1,379,700 
      • Replace sky lights $122,850 
      • Roof maintenance to modified bitumen $33,750 
      • Replace soft sealants $33,750 
      • Wet glaze windows $20,250 
      • Electrical and security upgrades $67,500 
      • Replace fencing $86,400 
      • Main service stainless steel enclosure $499,500 
      • Replace main switch on MCC panel $47,250 
      • Retrofit exterior LED marquee $35,000 
      • Replace boiler $114,750 
      • Replacement and upgrades to AHUs/VAV $469,935
        • FACILITY TOTAL $2,910,635
    • Parker Elementary
      • Replace front and back canopies $264,600 
      • Demolish gym and rebuild $3,375,000 
      • Replace exterior gym doors and paint $29,160 
      • Replace exterior soft sealants $60,750 
      • Wet glaze windows $13,500 
      • Replace fencing $84,375 
      • Repair support for main electrical feed $3,375 
      • Replace boiler $111,240 
      • Replace AHUs $693,900
        • FACILITY TOTAL $4,635,900
    • MECC I.T. PK3 San Jacinto Elementary School
      • Replace thru-wall flashing $56,700
      • Wet glaze windows $27,000 
      • Replace exterior soft sealants $33,750
      • Replace chiller (120 ton) $207,360
        • FACILITY TOTAL $324,810
    • Austin Middle School 
      • Repair roof over chiller room $27,000
      • Provide coping around perimeter $68,850 
      • Replace thru-wall flashing $145,800 
      • Exterior brick and stone work $47,250 
      • Re-point brick at classroom area $67,500 
      • Replace soft sealants $87,750 
      • Wetglaze all windows and doors $60,750 
      • Replace A/C and ductwork at gym $458,460 
      • Install VFD’s on cooling towers $50,625
        • FACILITY TOTAL $1,013,985
    • Central Media Arts Academy 
      • Remove dilapidated building near tennis court $3,375 
      • Repair roof $500,000 
      • Brick work $297,000 
      • Replace exterior wall panels $118,125 
      • Replace fencing $43,200 
      • Repair exterior LED marquee $35,000 
      • Replace chiller (350 ton) $675,000 
      • Upgrades to 1986 section of D/X units $486,000
        • FACILITY TOTAL $2,157,700
    • Collegiate Academy at Weis
      • Wet glaze windows $27,000 
      • Replace old section of chill water pipe $54,000 
      • Replace water heater $32,319
        • FACILITY TOTAL $113,319
    • Scott 
      • Resurface and paint tennis courts $162,000 
      • Replace fencing around tennis courts $101,250 
      • Repair built-up and armorlite roof $200,000 
      • Wet glaze windows $27,000
        • FACILITY TOTAL $490,250
    • Ball High School 
      • Replace carpet with floor tile $36,450
      • Gym renovations and asbestos abatement $405,000 
      • Replace lecture hall seating $6,480 
      • Repair windows and doors $54,000 
      • Repair built-up roof $500,000 
      • Repair sky lights $50,000   
      • Wet glaze newer windows $54,000 
      • Upgrade auditorium lighting $162,000 
      • Replace pump room fire pump and piping $76,477 
      • Replace 1995 section of cooling tower $842,535 
      • Chill/Hot water system renovations $433,350 
      • Replace domestic water heater $34,830
        • FACILITY TOTAL $2,655,122
    • Support Center 
      • Replace all carpet $72,900 
      • Replace soft sealants and repoint/seal brick $47,250 
      • Roof maintenance $13,500 
      • Replace A/C units in MIS $50,625 
      • Test and balance HVAC system $20,250 
      • Install new DX units $205,875
        • FACILITY TOTAL  $410,400
    • Annex
      • Replace carpet in various offices $72,900 
      • Exterior metal and brick work $80,000 
      • Replace A/C units and ductwork $202,365
        • FACILITY TOTAL $355,265
    • Bus Barn 
      • Install bus wash $135,000 
      • Replace/repair canopy over fuel pumps $67,500
        • FACILITY TOTAL $202,500
    • Technology + Buses 
      • Technology upgrades $2,000,000
      • New buses and fleet vehicles $2,500,000
        • Technology + Buses Total $4,500,000
    • Softball Field 
      • Replace back padding safety mats $8,100 
      • Replace exterior soft sealants $3,375
        • Softball Field Total $11,475
    • Baseball Field 
      • Install concrete in visitor dugout $4,050 
      • Facility for covered baseball & softball $1,485,000 
      • Replace fencing $101,250 
      • Replace exterior soft sealants $3,375
        • Baseball Field Total $1,593,675
    • Spoor Field 
      • New synthetic turf $1,350,000 
      • Resurface running track & repair sub-surface $405,000 
      • Replace exterior soft sealants $10,125
        • Spoor Field Total$1,765,125
    • Stadium
      • Repair/replace seating and upgrade lighting $500,000 
      • Replace exterior soft sealants $25,000 
      • Roof replacements on support buildings $69,300
        • Stadium Total $594,300
    • District-Wide 
      • Install security vestibules $234,225 
      • New dry erase boards and bulletin boards $200,000 
      • LED lighting upgrades and motion sensors $1,700,000 
      • Replace existing security cameras $500,000 
      • Exhaust fan replacements and upgrades $274,725 
      • Lead test drinking water $40,500
        • District-Wide Total $2,949,450
    •  

PROPOSED 2018 BOND TOTAL

$31,000,000

Bond Spending Pie Chart Image
Elementary Schools 40% • Technology & Transportation 15% • Middle Schools 10% • Safety & Efficiency 10% • High School 9% • Support Facilities 3%